Steerco #2 · Baseline lock · vendor selection
22 June 2026 · Phase 1 Engagement · Flip 360 / CoSai / YDT
1 · Executive summary
Four weeks in. Baseline KPIs captured for WS1 (acquisition CAC trending below $120 target) and WS2 (Stripe Connect test mode end-to-end validated). Counsel candidates have presented; recommendation locked for Steerco #3 ratification. BDM shortlist narrowed to two; Vertical-1 partner candidate identified and in early conversation. WS3 readiness model agreed at Steerco #1 now translating into 12-dimension curriculum draft. WS7 raise conversations remain at 4+ active. One amber item: WS6 partner-conversation pace dependent on BDM appointment.
1b · Bottom-up status reports for this Steerco
The executive summary above is the top-down narrative. Below are the bottom-up evidence-based status reports — what *is* happening in the repo and the live D1 database, sourced from evidence not from the PMO's narrative. Each report names gaps, identifies owners, and surfaces the decisions the Steering Committee needs to make. Read these before §5 (decisions).
2 · Workstream snapshot · at meeting
Position of every workstream on the four-state lifecycle as of this Steerco. Note: the data model on this site reflects the engagement-signing baseline — actual fortnightly transitions will be reflected here as they happen in Phase 1.
| WS | Title | Lead/Provider | Maturity |
|---|---|---|---|
| WS1 | Marketing & Digital Acquisition | Corrina McGowan YDT |
Implemented |
| WS2 | Commission Engine | Carla Oliver CoSai |
Implemented |
| WS3 | Founder Capability | Mathew Punter (coachee) CoSai |
Scoped |
| WS4 | Legal & Corporate Structure | TBA CoSai |
Scoped |
| WS5 | Platform Engineering & Data | AI-augmented workforce CoSai |
Absorbed by design |
| WS6 | Vertical Partnerships & BDM | TBA CoSai |
Built |
| WS7 | Investor Relations & Capital Strategy | Carla Oliver (CFO hat — separable from CoSai retainer hat) CoSai |
Implemented |
3 · Maturity transitions · since last Steerco
No state transitions in this period. Workstreams operating against milestone plan.
4 · Milestones · review at this meeting
| WS | Week | Milestone | Triggers |
|---|---|---|---|
| WS1 | W4 | Baseline acquisition KPIs captured · CAC ≤ $120 target ratified | No state change |
| WS2 | W4 | Stripe Connect test mode validated end-to-end · idempotency hardening complete | No state change |
5 · Decisions today · awaiting Client sign-off
WS2 · Stripe Connect — sprint, re-baseline, or accept slip
WS2 · Ratify ADR-7 via live six-guarantees demo at SC#2
WS2 · Lock observability vendor decision
WS2 · Acknowledge marketing-copy-vs-runtime delta and approve hardening sprint plan
6 · RAID · amber & red escalations
| ID | Type | Severity | WS | Title & mitigation | Owner |
|---|---|---|---|---|---|
| R001 | Risk | Amber | WS4 | Fractional counsel engagement timing — must land by Steerco #3 Three candidates engaged early; recommendation tabled at Steerco #2 |
Carla (PMO) |
| R002 | Risk | Amber | WS6 | Senior BDM appointment timing — Vertical-1 partner conversations dependent on BDM seat being filled PMO holds partner conversations until BDM appointed; shortlist narrowed at Steerco #2 |
Carla (PMO) |
| A006 | Assumption | Amber | WS2 | Compliance gate default checklist: claims-substantiated · disclosure-present · brand-approved · legal-cleared Settings → Compliance Gates exposes per-asset-type checklist. Corrina + counsel ratify the production set at Steerco #3 before any /crm/* compliance gate goes live. Demo uses 4-default seed. |
Corrina (consulted) · Carla (accountable) |
| A007 | Assumption | Amber | WS2 | Cooling-off period defaults to 14 days, vertical-agnostic Settings → Cooling-off exposes per-vertical / per-commission-type duration. Demo seeds 14 days flat; Matt ratifies vertical-specific durations at Steerco #3 before commission engine production cutover. |
Matt (consulted) · Carla (accountable) |
| A008 | Assumption | Amber | WS2 | Commission base rate placeholder 10% until Matt-signed policy lands Settings → Commission Engine exposes per-vertical rate + tiered structure (volume / tenure / mix bonus). Demo seeds 10% flat placeholder. Production /me/commissions/* gated until Matt-signed policy is loaded into config_commission_policy. |
Matt (consulted) · Carla (accountable) |
| A015 | Assumption | Amber | WS2 | Sales-internal + CS suite embodiers TBA until Phase 2 BAU hires Phase 1 demo uses TBA placeholders. Settings → Roles & Access allows assignment of real users to Sales / CS roles once Phase 2 BAU hires land. No code change. |
Carla (WS2 Lead) |
| R003 | Risk | Amber | WS2 | Settings versioning + retroactive recalc risk on commission engine Commission policy changes must be effective-dated, never retroactive without explicit recalc approval. Historical commission records carry the policy-version they were calculated against. Dry-run preview before save shows "would change N commissions, total $X delta". |
Carla (WS2 Lead) |
| R004 | Risk | Amber | WS2 | Misconfigured Settings could break commission engine or compliance gate Settings admin permission gated to specific roles (CFO + Compliance Officer). Financial-rule changes require dual sign-off. All changes audited with before/after diff. Recovery: every settings row versioned, one-click revert. |
Carla (WS2 Lead) |
| D002 | Dependency | Amber | WS2 | Final commission policy from Matt before /me/commissions/* production cutover Demo seeds 10% placeholder. Production /me/commissions/* blocked until Matt-signed policy loaded into config_commission_policy. Settings → Commission Engine exposes the editor; Matt completes by Steerco #3. |
Matt (consulted) · Carla (accountable) |
| D003 | Dependency | Amber | WS2 | AU regulatory clearance on member-side commission framing (AFSL / AUSTRAC / consumer law) Counsel-engaged sprint Steerco #2 → #3 covers AFSL applicability for referral payments, AUSTRAC AML/CTF for member payouts, ACL disclosure obligations. /me/commissions/* + /crm/compliance/* surfaces parameterised by counsel-ratified rules in Settings. |
Compliance (Pine Lawyers, consulted) · Carla (accountable) |
| I001 | Issue | Amber | WS2 | Architectural pivot — /crm-demo/* must be a working CRM tool, not a styled walkthrough Decision D-PIVOT-CRM (Carla, 2026-06-24): /crm-demo/* refactored from visual narrative pages to a real three-pane CRM workspace backed by D1. New schema (migration 0003): contacts, deals, activities, tickets, notes, settings_rows. Sarah Chen + 24 demo contacts seeded. BD/Sales/CS/CMO workspaces share contact data so the cross-role thread is real, not narrated. Pipeline kanban actually drags; settings actually edit; cooling-off change actually propagates. Demo data only — /crm-demo/* gate held; /crm/* untouched. Resolves the risk Matt and Corrina decline sign-off on a visual mock. |
Carla (WS2 Lead) · Claude (build) |
7 · Forward look · the next two weeks
Counsel engaged · curriculum drafted. Six weeks in — the structural pivot point of Phase 1. WS4 counsel engaged this period; standard SaaS T&Cs draft underway. WS3 founder-readiness curriculum drafted; Mathew accepts at this meeting (transitions WS3 to Built). WS6 Vertical-1 MoU drafted by counsel; partner sign-off t…