Flip 360 Commission Platform
Source
Live board Workstream ops Registers Steerco papers Scoping · CRM CRM · truth doc CRM · features map CRM design · Contact 360° Deal room Hardening backlog Learn (ADKAR) Framework
Deal room · workstream cost performance · WS2

WS2 · Commission Engine + CRM

Time
Scope
Budget
Variance
$-1,250
Committed budget
$13,250
ex-GST · per engagement letter
Costs to date
$8,000
ex-GST · invoiced + paid
Costs to complete
$6,500
ex-GST · forecast remaining
Variance
$-1,250
over budget

 Budget breakdown (ex-GST)

PMO services (CoSai oversight)$7,500
AI workforce tokens$5,000
Third party (legal, brand, etc.)$0
Contingency (10% on PMO services)$750
Total WS2 budget$13,250

 Scope commitments (this WS will deliver by handover)

 Costs to date · $8,000 ex-GST

Date Category Description Ex-GST Inc.GST Invoice Status
2026-05-21 PMO services PMO services · Phase 1 Month 1 (May→June 2026) · WS2 allocation (commission engine E2E) $2,500.00 $2,750.00 CSC-INV-2026-001 PAID
2026-06-22 AI workforce tokens AI workforce tokens · CRM scoping sprint (WS2-B007 · Mon 22 → Fri 26 Jun 2026) · PAID 22 Jun 2026 $500.00 $550.00 CSC-INV-2026-002 PAID
2026-06-22 AI workforce tokens AI workforce tokens · commission engine build credits (asset delivered: live /app, /legal, /chain) $5,000.00 $5,500.00 CSC-INV-2026-003 INVOICED

 Costs to complete · $6,500 ex-GST forecast

Expected Category Description Ex-GST Confidence Trigger
2026-07-01 PMO services Phase 1 Month 2 PMO services · WS2 allocation (July 2026) $2,500.00 HIGH CSC-INV-2026-004 issued early July, payable in advance
2026-08-01 PMO services Phase 1 Month 3 PMO services · WS2 allocation (August 2026) $2,500.00 HIGH CSC-INV-2026-005 issued early August, payable in advance
2026-07-01 AI workforce tokens WS2 contingency · AI tokens for CRM build sprint (post-SC#2 approval) and overflow capacity $1,500.00 MEDIUM Steerco #2 approval of CRM build sprint budget (Mon 29 Jun 2026)

 OTOSOB judgement · as of 2026-06-22

Time
Scope
Budget

PMO Director's rationale: Commission engine delivered. CRM scoping sprint in progress (D111 P0). Stripe Connect rolled over to current sprint — BLOCKED on API keys (escalation to SC#2 if not unblocked Fri 26 Jun). Time = amber due to Stripe blocker. Scope + budget = green.

Back to deal room WS2 live ops Invoices register Receipts register